Community Meeting – May 16, 2018
Progress continues at the Transbay Transit Center construction site with the continuation of sidewalk concrete placement at the Ground Level especially along Minna and Natoma streets. Metal ceiling panel installation along with mechanical, electrical and plumbing systems wire termination/commissioning are all underway, as well.
Join us for a community meeting on Wednesday, May 16, 2018 to learn more about the construction activities. This meeting will be held at 12 noon at the TJPA offices located at 201 Mission Street, Suite 2100. We appreciate you taking your lunch hour to learn about this innovative project, and welcome you to bring food or drinks to this meeting.
What: Community Meeting: Construction Update
When: Wednesday, May 16, 2018 Time: 12 noon
Where: Transbay Joint Powers Authority
201 Mission Street, Suite 2100
San Francisco, CA 94105