May 10, 2019 - UPDATE ON TEMPORARY CLOSURE OF SALESFORCE TRANSIT CENTER

Update:

The repair and reinforcement at Salesforce Transit Center are complete.
Shoring has been removed from Fremont and First streets and all lanes are restored to their original condition.
Nighttime street closures will continue throughout May to restore lights, MUNI overhead lines, …

(click to download)

April 25, 2019 - UPDATE ON TEMPORARY CLOSURE OF SALESFORCE TRANSIT CENTER

Background:

The Transbay Joint Powers Authority (TJPA), owner and operator of the Salesforce Transit Center, temporarily closed the facility in September 2018 as a precaution after workers discovered fissures in two steel beams on the bus deck above Fremont Street. A repair and reinforcement project will be …

(click to download)

April 19, 2019 - TRANSBAY JOINT POWERS AUTHORITY ANNOUNCES NIGHTTIME STREET CLOSURE TO REMOVE FREMONT STREET TEMPORARY SHORING

 San Francisco, CA – The Transbay Joint Powers Authority (TJPA) today announced that starting Sunday, April 21, 2019 the temporary shoring system on Fremont Street will be removed. The overnight work will take place Sundays through Fridays for the next four weeks …

(click to download)

April 10, 2019 - UPDATE ON TEMPORARY CLOSURE OF SALESFORCE TRANSIT CENTER

Background:

The Transbay Joint Powers Authority (TJPA), owner and operator of the Salesforce Transit Center, temporarily closed the facility in September 2018 as a precaution after workers discovered fissures in two steel beams on the bus deck above Fremont Street. Before reopening, the TJPA must:

Repair …

(click to download)

March 29, 2019 - UPDATE ON TEMPORARY CLOSURE OF SALESFORCE TRANSIT CENTER

Background:

The Salesforce Transit Center is temporarily closed. In September 2018, workers discovered two fissures in steel beams on the bus deck above Fremont Street. After several inspections and out of an abundance of caution, the Transbay Joint Powers Authority (TJPA) temporarily closed the Transit Center. …

(click to download)

February 27, 2019 - UPDATE ON TEMPORARY CLOSURE OF SALESFORCE TRANSIT CENTER

Background:

The Salesforce Transit Center is temporarily closed. In September 2018, workers discovered two fissures in steel beams on the bus deck above Fremont Street. After several inspections and out of an abundance of caution, the Transbay Joint Powers Authority (TJPA) temporarily closed the Transit Center.

This is a localized issue within …

(click to download)

February 1, 2019 - TRANSBAY JOINT POWERS AUTHORITY ANNOUNCES REPAIRS TO BEGIN AT TRANSIT CENTER

 
San Francisco, CA – The Transbay Joint Powers Authority (TJPA) announced today that repair and reinforcement work to address the fractured steel beams at the Transit Center is underway and First Street work begins on site this weekend. The Metropolitan Transportation Commission’s independent …

(click to download)

January 22, 2019 - UPDATE ON TEMPORARY CLOSURE OF SALESFORCE TRANSIT CENTER

Background:

The Salesforce Transit Center is temporarily closed. In September 2018, workers discovered two fissures in steel beams on the bus deck above Fremont Street. After several inspections and out of an abundance of caution, the Transbay Joint Powers Authority (TJPA) temporarily closed the Transit Center. …

(click to download)

January 4, 2019 - UPDATE ON TEMPORARY CLOSURE OF SALESFORCE TRANSIT CENTER

Background:

The Salesforce Transit Center is temporarily closed. In September 2018, workers discovered two fissures in steel beams on the bus deck above Fremont Street. After several inspections and out of an abundance of caution, the Transbay Joint Powers Authority (TJPA) temporarily closed the Transit …

(click to download)

December 31, 2018 - UPDATE ON TEMPORARY CLOSURE OF SALESFORCE TRANSIT CENTER

Background:

The Salesforce Transit Center is temporarily closed. In September 2018, workers discovered two fissures in steel beams on the bus deck above Fremont Street. After several inspections and out of an abundance of caution, the Transbay Joint Powers Authority (TJPA) temporarily closed the Transit Center. …

(click to download)

December 13, 2018 - UPDATE ON TEMPORARY CLOSURE OF SALESFORCE TRANSIT CENTER

Background:

The Salesforce Transit Center is temporarily closed. In September 2018, workers discovered two fissures in steel beams on the bus deck above Fremont Street. After several inspections and out of an abundance of caution, the Transbay Joint Powers Authority (TJPA) temporarily closed the Transit Center.

This is a localized issue within …

(click to download)

November 27, 2018 - UPDATE ON TEMPORARY CLOSURE OF SALESFORCE TRANSIT CENTER

Background:

The Salesforce Transit Center is temporarily closed. In September 2018, workers discovered two fissures in steel beams on the bus deck above Fremont Street. After several inspections and out of an abundance of caution, the Transbay Joint Powers Authority (TJPA) temporarily closed the Transit Center.

This is a localized issue within …

(click to download)

November 13, 2018 - UPDATE ON TEMPORARY CLOSURE OF SALESFORCE TRANSIT CENTER

The Salesforce Transit Center is temporarily closed. In September 2018, workers discovered two fissures in steel beams on the bus deck above Fremont Street. After several inspections and out of an abundance of caution, the Transbay Joint Powers Authority (TJPA) temporarily closed the Transit Center.
This is a …

(click to download)

November 8, 2018 - UPDATE ON TEMPORARY CLOSURE OF SALESFORCE TRANSIT CENTER

The Salesforce Transit Center is temporarily closed. In September 2018, workers discovered two fissures in steel beams on the bus deck above Fremont Street. After several inspections and out of an abundance of caution, the Transbay Joint Powers Authority (TJPA) temporarily closed the Transit Center.

This is a localized issue within …

(click to download)

October 25, 2018 - UPDATE ON TEMPORARY CLOSURE OF SALESFORCE TRANSIT CENTER

The Salesforce Transit Center is temporarily closed. In September 2018, workers discovered two fissures in steel beams on the bus deck above Fremont Street. After several inspections and out of an abundance of caution, the Transbay Joint Powers Authority (TJPA) temporarily closed the Transit Center.

This is a localized issue within …

(click to download)

October 17, 2018 - TJPA Statement Regarding Complaint Filed in San Francisco Superior Court Regarding Salesforce Transit Center

The Transbay Joint Powers Authority (TJPA) made the following statement today regarding a complaint filed in San Francisco Superior Court Regarding Salesforce Transit Center:

“The Transbay Joint Powers Authority will hold Webcor/Obayashi Joint Venture responsible for their contractual commitment to deliver this project to the people of the Bay Area and …

(click to download)

October 14, 2018 - FREMONT STREET TO REOPEN FOR MONDAY MORNING COMMUTE

San Francisco, CA – The Transbay Joint Powers Authority (TJPA) announced today that work on a four-level shoring system beneath the temporarily closed Salesforce Transit Center on Fremont Street between Howard and Mission streets is complete. Fremont Street will reopen in time for the Monday morning commute.

(click to download)

October 10, 2018 - Temporary Closure of Salesforce Transit Center

Update

October 10, 2018

Work on a shoring system at the Salesforce Transit Center at Fremont Street between Howard and Mission streets continued today and will continue into early next week, moving the scheduled reopening date of the one block closure. The street will reopen to traffic and the public on Wednesday, …

(click to download)

October 5, 2018 - Temporary Closure of Salesforce Transit Center

Update

The Salesforce Transit Center is temporarily closed. On the morning of Tuesday, September 25, 2018, workers discovered a fissure on a steel beam in the ceiling of the third level bus deck near Fremont Street. After several inspections and out of an abundance of caution, the TJPA temporarily closed the …

(click to download)

October 5, 2018 - TJPA ANNOUNCES UPDATES ON TEMPORARY CLOSURE AT SALESFORCE TRANSIT CENTER, FREMONT STREET SHORING & REINFORCEMENT PLANS

San Francisco, CA – The Transbay Joint Powers Authority (TJPA) announced today that work on a shoring system beneath the Salesforce Transit Center at Fremont Street between Howard and Mission streets continued today and that Fremont Street is scheduled to reopen by October 12, 2018 in time for the morning …

(click to download)

October 3, 2018 - Temporary Closure of Salesforce Transit Center

Updated October 3, 2018

The Salesforce Transit Center is temporarily closed. On the morning of Tuesday, September 25, 2018, workers discovered a fissure on a steel beam in the ceiling of the third level bus deck near Fremont Street. After several inspections and out of an abundance of caution, the TJPA …

(click to download)

September 28, 2018 - TJPA ANNOUNCES UPDATES ON TEMPORARY CLOSURE AT SALESFORCE TRANSIT CENTER, PEER REVIEW AND NEW PORTAL FOR PUBLIC DOCUMENTS

Public Documents Portal- Find reviews, design reports, contracts, inspections, etc. More information will be added on an ongoing basis. https://transbaycenter.app.box.com/s/sfivpl21ii3h27ahbhmhd04uonq5nv5d

(click to download)

September 27, 2018 - TJPA ANNOUNCES UPDATES ON TEMPORARY CLOSURE AT SALESFORCE TRANSIT CENTER AND THE LAUNCH OF A MEDIA HOTLINE

San Francisco, CA – The Transbay Joint Powers Authority (TJPA) announced today that crews continued their work throughout the night to assess and test steel beams and prepare the site for a shoring installation at the Salesforce Transit Center. Crews removed ceiling panels and moved light fixtures and utilities and …

(click to download)

September 26, 2018 - TJPA ANNOUNCES INITIAL INSPECTION RESULTS FOR SALESFORCE TRANSIT CENTER

San Francisco – The Transbay Joint Powers Authority (TJPA) announced today results of initial inspections to steel beams at the Salesforce Transit Center and efforts underway to open Fremont Street and the transit center as soon as safely possible.

(click to download)

September 25, 2018 - TJPA ANNOUNCES TRANSIT IMPACTS DUE TO SALESFORCE TRANSIT CENTER TEMPORARY CLOSURE

San Francisco – There are several transit and traffic impacts due to the temporary closure of the Salesforce Transit Center and the closure of Fremont Street between Mission and Howard, particularly during peak commute hours. Motorists are kindly asked to avoid driving downtown, transit riders are encouraged to allow extra …

(click to download)

September 25, 2018 - STATEMENT ON TEMPORARILY CLOSING SALESFORCE TRANSIT CENTER

San Francisco – Crews today discovered a fissure in one of the steel beams in the ceiling of the third level Bus Deck on the eastern side of the Salesforce Transit Center near Fremont Street. Out of an abundance of caution, the Transbay Joint Powers Authority, after conferring with design …

(click to download)

September 24, 2018 - TJPA: Ruling limits taxpayer liability in Millennium Tower legal costs fight

San Francisco – The Transbay Joint Powers Authority (TJPA) announced Monday that a court ruling last week may require the TJPA to pay in the future just a fraction of the legal costs sought by Mission Street Development (MSD), the developer of the sinking and tilting Millennium Tower.

(click to download)

August 10, 2018 - MAYOR BREED, LEADER PELOSI AND STATE AND REGIONAL PARTNERS CELEBRATE COMPLETION OF TJPA’s SALESFORCE TRANSIT CENTER

Mayor London Breed, House Democratic Leader Nancy Pelosi and regional, state and federal leaders joined the TJPA to celebrate the completion of the new Salesforce Transit Center.

(click to download)

July 12, 2018 - TJPA ANNOUNCES OPENING DATES, CIVIC CELEBRATION AND NEW RETAIL LEASES AT SALESFORCE TRANSIT CENTER

The TJPA announced that the Salesforce Transit Center officially opens to the public at Noon on Saturday, August 11, 2018 with a Neighborhood Block Party, with inaugural Transbay bus service by AC Transit and others beginning August 12, 2018. The TJPA also announced that nearly half of the permanent retail …

(click to download)

May 15, 2017 - Lincoln Property Company, with partners Colliers International, Biederman Redevelopment Ventures, and Pearl Media, selected to operate and manage